I need a solution
Good Afternoon all,
We recently had to manually kick off some jobs due to they failing and not being noticed until they were outside of their window. Due to them being kicked off manually the following weekend when they were scheduled (not by calendar) to run they did not kick off. We use frequency on everything but monthly and yearly jobs.
These jobs were weekly full backups. The frequency was set to 1 week, my thought to stop this from ever happening again is to set the frequency to 1 day, that way no matter when we have the weekly job scheduled to run it will run even if we had to do an manual the night before.
Is there any harm to doing this?